4.3. Fastening the engine - the transmission

4-cylinder engine

1. M12x130 screw, 80 N · m

2. 2 M12x60 screws, 80 N · m

3. M12x100 screw, 80 N · m

5. M8x32 screw, 25 N · m

6. M8x12 screw, 25 N · m
The directing sleeves for centering in positions A and B

5-cylinder engine

1. M12x60 screw, 80 N · m

2. 3 M12x70 screws, 80 N · m

3. M12x100 screw, 80 N · m

4. M12x130 screw, 80 N · m

5. 3 M8x45 screws, 25 N · m
The directing sleeves for centering in positions A and B

PERFORMANCE ORDER
1. Alternately shaking to lift the engine and the transmission assembled. At the same time to have the right half shaft so that it adjoined to a flange shaft of the transmission.

Prevention

For installation of a bolt of fastening of a support of units at the left on a body, it is necessary to establish a basic pin of a support of the engine and a spindle of removable adaptation (shooter) precisely on one line. To remove removable VW-3184 adaptation only when screws of fastening of the left support of units are tightened.


2. 4-cylinder engine: to screw a protective protection an exhaust pipe - the fuel tank.
3. To connect a forward exhaust pipe to the additional muffler or the catalyst (see subsection 2.19.1).
4. To wring out the stabilizer of both connecting drafts against the stop up to provide space for an exhaust pipe.
5. To tighten a bearing arm on the transmission and on a rubber-metal support the moment of 65 N · m.
6. If acted, to establish electrical wires and pipelines.
7. To remove removable VW-3184 adaptation.
8. To unscrew a support of the VW 3230/3227 engine.
9. To install a power shaft of a speedometer on the case of the bearing of the right half shaft of the engine.
10. To 8/92 (date of issue of a box 09.08.92):
     – to establish a back support the engine - the transmission without tension;
     – to tighten screws (A) the moment of 65 N · m (only if the transmission support was removed);
     – to tighten screws (V) the moment of 45 N · m.
Prevention

After replacement of the transmission or its repair it is necessary to measure thickness of a compensation plate between the console and the case of the transmission again. For this purpose to measure distance between the console and the transmission and to establish between them a plate 0,5 mm or 1,0 mm thick. If less than 0,5 mm, a plate not to establish a gleam.


11. With 8/92 (date of production of the transmission 10.08.92) the changed back support of the transmission is established:
     – openings (A) are increased from 10 mm to 12 mm;
     – old six-sided M10 screws of fastening of a support of a box on an arm of hinged units are replaced with new six-sided M16 screws (C) – the new back support of a box cannot be installed in old machines.
12. With 8/92:
     – to establish a back support the engine - the transmission without tension;
     – to tighten screws (A) the moment of 100 N · m;
     – to tighten screws (V) the moment of 40 N · m;
     – the screw (C) to tighten the moment 270 N · m.
13. Conditioner: to screw the compressor.
14. 4-cylinder engine: to establish the lower protective protection of a flywheel.
15. 4-cylinder engine: to screw in fastening screws the engine - the transmission over the bearing case (the inhaling moments: the M8 screw – 25 N · m, the M12 screw – 80 N · м).
16. To tighten bolts of fastening of the bearing transmission on the engine and the case of the bearing so: to establish bolts (A) and (In). In the beginning to tighten bolts (A), then bolts (In).
17. 5-cylinder engine: to install the generator.
18. Diesel engine: to put on a vacuum hose of the amplifier of brakes the vacuum pump.
19. To screw connection with the mass of a box of broadcasts arms of the bearing.
20. To establish a starter.
21. To screw the screw of the shock-absorber and connecting draft of the stabilizer on the right the moment of 160 N · m.
22. To attach the right half shaft of the transmission.
23. To establish the left half shaft.
24. To remove basic VW-3250 adaptation.
25. 4-cylinder diesel engine: to establish and adjust ropes on the engine (cm. subsection 2.17.5 and subsection 2.17.6).
26. Petrol engine: to install vacuum шлаг the amplifier of brakes on the engine.
27. To wrap fastening screws the engine - the transmission from above. Inhaling moments: the M8 screw – 25 N · m; the M12 screw – 80 N · m.
28. To attach an electrical wiring to the pipeline.
29. To screw the pipeline of cooling liquid from a broad tank on a water pomp, on a starter.
30. To install an arm of a power shaft of a speedometer on the transmission.
31. At cars with the mechanical drive of coupling to fix a coupling rope on the transmission and an arm of the bearing of the transmission.
32. Mechanical drive of coupling: to squeeze out a coupling pedal against the stop not less than 5 times, then to check operation of the adjusting device (see subsection 3.4).
33. At cars with the hydraulic drive of coupling: to screw the working cylinder on the transmission the moment of 25 N · m.
34. To take out an assembly pin or the M8x22 screw from an opening of the transmission and to close an opening a stopper.
35. To establish and adjust the mechanism of switching to the transmission.
36. To establish on former places of fastening of an electrical wiring to hoses of cooling liquid.
37. To connect, according to tags an adhesive tape, cables of the transmission and a starter.
38. To establish a radiator on the place (cm. subsection 2.16.2.1).
39. To connect a weight(s) cable to the rechargeable battery.
Prevention

To connect the rechargeable battery only at the switched-off ignition. Otherwise the control unit of system of injection will fail.


40. To determine time on hours.
41. To enter an anticreeping code into the radio receiver.